U-Bahnhof München-Mariënplatz
Description:
|
The safety level of Munich-Marienplatz Metro Station was increased as a part part of the preparations for the 2006 World Cup. Zitron Nederland installed the smoke extraction system.
|
Tunnel length:
|
ca. 750m
|
Ventilation method:
|
Longitudinal ventilation with smoke extraction at platform
|
Scope of supply:
|
4 jet fans with a diameter of 600 mm and a thrust of 400 N
2 extraction fans suitable for one-off operation at 400 °C for 90 minutes. silencers, dampers, reducers, fire dampers, smoke extraction ducts and partitions |
Delivery:
|
Factory acceptance testing, shipping, installation, commissioning and site acceptance testing.
|
Completion date:
|
May 2006
|